How Long Does a Kitchen Renovation Take? A Day-by-Day Fitting Timeline

Greentek Energy Ltd kitchen fitting timeline from strip out and first fix to worktops and finishing, with a wall calendar
In this article⌄

Most kitchen renovations take between a few days and four weeks once work starts on site. A simple update to an existing kitchen can be done in under a week. A like-for-like replacement usually takes one to two weeks. A full renovation with a new layout, moved plumbing and stone worktops usually takes around 14 working days, or about three weeks. Most of that time goes on plaster drying and the wait for worktops to be made.

Knowing how long a kitchen renovation takes helps you plan meals, time off work and deliveries. This guide walks through the work day by day, explains why some kitchens take longer than others and ends with a checklist to help you keep your project on schedule.

Key Facts at a Glance

QuestionShort answer
Simple kitchen refurbishmentOften 2 to 5 working days when the units and layout stay the same
Like-for-like replacementAround 5 to 10 working days with laminate worktops
Full renovation with a new layoutAround 14 working days (about three weeks) with stone worktops
Biggest single delayStone worktops take 7 to 10 working days to make after templating
Plaster drying before paintingAt least 5 to 7 days, longer in cold or damp rooms
Time without a working kitchenFrom strip-out until the sink and hob are reconnected
Who can connect a gas hob?Only a Gas Safe registered engineer, by law

How Long Does a Kitchen Renovation Take for Each Type of Project?

The answer depends on how much of the room changes. Swapping doors and worktops on an existing layout takes days. Moving the sink, adding circuits and fitting stone worktops takes weeks. Removing a wall or building an extension adds structural work and inspections, which adds more time again.

Project typeWhat it usually involvesTypical time on site (guide only)
Kitchen refurbishmentNew doors, worktops, handles or appliances on the existing units2 to 5 working days
Like-for-like replacementNew units and laminate worktops in the same layout5 to 10 working days
Full kitchen renovationNew layout, moved plumbing, new sockets, plastering, flooring and stone worktopsAround 14 working days
Open-plan knock-throughA full renovation plus removing a wall and fitting a steel beam4 to 6 weeks
Kitchen extensionNew foundations, walls and roof before the kitchen goes inSeveral months

These ranges reflect how the work is usually sequenced. Your own timeline depends on the size of the room, the materials you choose and what is found once the old kitchen comes out. Our kitchen renovations team includes a timeline with every quote, so you know what to expect before work begins.

If you are adding space as well, the build comes first and the kitchen follows. Our single storey extension cost guide explains what that stage involves.

Time on Site Is Only Part of the Story

The figures above cover the time trades spend in your home. Before that, there is a planning stage for the survey, design, quote and ordering. This stage often takes longer than the work itself. Made-to-order and painted kitchens can take several weeks to arrive, so ask your supplier for a confirmed delivery date before you agree a start date.

Kitchen Refurbishment vs Renovation: How the Timelines Compare

When people compare a kitchen refurbishment vs renovation, the main difference is what stays. A refurbishment keeps the layout, the units and usually the services. A renovation changes the room itself. That is why one takes days and the other takes weeks.

What a Refurbishment Usually Involves

  • New cupboard doors, drawer fronts and handles
  • Replacement worktops cut to fit the existing units
  • New appliances in the same positions
  • A fresh splashback and redecoration

Because the sink, hob and sockets stay where they are, there is no first fix, no plastering and very little waiting between trades.

What a Renovation Usually Involves

  • Removing the old kitchen back to bare walls
  • Moving pipes, adding circuits or rerouting gas
  • Replastering, new flooring and new lighting
  • Sometimes widening an opening or removing a wall

Each of these adds a stage, and some stages cannot start until the one before is finished. If you are weighing up the budget side of this choice, our kitchen renovation cost guide compares the two in detail.

What Happens in the Weeks Before Work Starts?

The weeks before strip-out decide whether the job runs on time. This is when the room is measured, the layout is fixed, everything is ordered and any approvals are arranged. A well-planned start is the best protection against delays later.

Survey and Design

A proper survey checks more than the room size. It looks at the condition of the walls and floor, where pipes and cables run and whether the electrics can take new appliances. This is also the time to decide where sockets, lights and the extractor will go. Changing these later means cutting into finished walls.

Ordering Units, Worktops and Appliances

Lead times vary widely. Some ranges are held in stock, while made-to-order or painted units take longer. Order appliances early as well, because the fitter needs their exact sizes. When deliveries arrive, check every box against the order. One missing corner unit can stop the whole fit.

Approvals for Structural Work

If you want an open-plan room, removing a load-bearing wall needs structural calculations, a steel beam and building regulations approval. These need to be arranged before the wall comes down.

Getting Your Home Ready

Empty the cupboards, clear the route from the front door and set up somewhere to make simple meals. Our guide to living in your house during a renovation has practical tips on setting up a temporary kitchen.

Kitchen Installation Stages: A Day-by-Day Fitting Timeline

The timeline below shows typical kitchen installation stages for a full renovation with a new layout and stone worktops, completed in 14 working days. That is just under three weeks. Simpler jobs skip some stages. Every kitchen is different, but the order of work stays much the same.

Working daysStageWhat happens
Day 1Strip-outServices made safe, old kitchen removed, walls and floor checked
Days 2 to 3First fixNew pipework, cables, back boxes and any gas pipe changes
Day 4PlasteringWalls and ceiling skimmed or boarded
Days 5 to 6Flooring and unitsFloor prepared, base and wall units fitted and levelled
Day 6TemplatingStone worktops measured once base units are secure
Days 7 to 12Worktop waitWorktops made while painting and finishing work continues
Day 13Worktop fittingWorktops fitted, sink and hob connected and tested
Days 13 to 14Tiling and second fixSplashback tiled, sockets and lights finished, appliances fitted
Day 14Snagging and handoverFinal checks, clean and walkthrough

With laminate worktops, the worktop wait disappears. The same kitchen would usually be finished in around 8 to 10 working days, depending on how quickly the plaster dries for painting.

Day 1: Strip-Out and Making Safe

The first job is protecting the rest of your home. Floors and doorways are covered, and the water, electrics and gas are isolated. The old units, worktops and appliances then come out, along with any tiles that are being replaced.

Once the room is empty, problems that were hidden behind the old kitchen become visible. Damp, rotten floorboards, loose plaster and old wiring are the most common. It is better to find them now than after the new units are in. In homes built or refurbished before 2000, old floor tiles, textured ceilings or pipe boxing can contain asbestos. If anything suspicious turns up, work in that area stops until it has been tested.

Days 2 to 3: First Fix Plumbing, Electrics and Gas

First fix is the work that ends up hidden inside walls and floors. Pipes are run to the new sink and appliance positions. Cables are run for new sockets, lighting and the cooker circuit. If the hob is moving, the gas supply is rerouted.

What Do First Fix and Second Fix Mean?

First fix covers everything installed before plastering, such as pipes, cables and back boxes. Second fix covers the visible finishing after plastering, such as sockets, switches, taps and appliance connections. Thinking in these two stages explains why a socket cannot easily be moved once the walls are finished.

New electrical circuits must meet building regulations, and you should receive an electrical certificate when the work is complete. Any work on gas pipework or a gas hob must be done by a Gas Safe registered engineer. Before the work starts, you can check an engineer on the Gas Safe Register to confirm they are qualified for the job.

Day 4: Plastering and Drying Time

Walls that have been chased for cables or damaged during strip-out are made good. In most renovations the walls are skimmed, and some ceilings are boarded and skimmed too. Fresh plaster needs at least five to seven days to dry before a mist coat, and longer in a cold or poorly ventilated room. Units can usually be fitted while the plaster dries, but painting has to wait.

Days 5 to 6: Flooring and Fitting the Units

Depending on the material, flooring is laid either before the units go in or afterwards up to the plinths. Tiled floors often go down first. Some vinyl and laminate floors are fitted at the end.

The base units are then fixed and levelled, followed by the wall units, tall housings and end panels. If you are wondering how long to fit a kitchen once the room is ready, the fitter's work on an average kitchen adds up to around three to eight days. It is spread across this stage and the worktop, door and appliance work later. Island units, larder housings and integrated appliances add time.

Day 6: Worktop Templating

Laminate and wooden worktops are usually cut and fitted on site straight after the units. Stone, quartz and solid surface worktops are different. They are templated, which means measured precisely with a laser or template boards, once the base units are fully fixed. Templating usually takes a few hours.

Days 7 to 12: The Worktop Wait

This is the gap that surprises most homeowners. Quartz and granite worktops typically take 7 to 10 working days to make after templating, and solid surface worktops can take longer. This 14-day timeline assumes the quicker end of that range. If your worktops take the full 10 working days, the finish date moves back by about three days. During this time there is no sink or hob, so the kitchen is still out of use.

The time is not wasted. Once the plaster is dry, the ceiling and walls can be painted. Lighting, plinths and other finishing work can go ahead, and the fitter can return when the worktops arrive.

Day 13: Worktops, Sink and Hob

Fitting stone worktops usually takes a few hours. The sink is then installed and plumbed in, the tap is connected and the water is turned back on. The hob is connected and tested, and gas hobs are checked by the Gas Safe engineer before they are used. For many households, this is the day the kitchen becomes usable again.

Days 13 to 14: Splashback Tiling and Second Fix

Splashback tiles go on after the worktops, because they sit on top of them. Grout normally needs around 24 hours before it is cleaned or gets wet. At the same time, the electrician fits sockets, switches and under-cabinet lights, and the appliances are slid into place and connected.

Day 14: Snagging and Handover

Snagging means checking every detail and fixing small faults. Doors are adjusted so the gaps are even. Drawers are tested, sealant lines are checked and every appliance is run. You should then be given the paperwork, including electrical and gas certificates, any building control sign-off and your warranty details.

Kitchen Fitting Timeline: Laminate vs Stone Worktops

Your worktop choice has a bigger effect on the kitchen fitting timeline than almost anything else. Laminate is fitted as part of the main installation. Stone adds a measuring visit, a manufacturing wait and a return visit.

StageLaminate or wood worktopsStone, quartz or solid surface
How worktops are measuredCut on site during fittingTemplated once base units are fixed
Time to makeNone, cut from stock lengths7 to 10 working days for quartz or granite
When the sink and hob work againUsually the day after the units are fittedOnce the stone worktops are installed
Typical full renovationAbout 8 to 10 working daysAbout 14 working days

Neither choice is wrong. If stone is important to you, plan for the gap from the start. When you compare quotes, ask each installer how long to fit a kitchen with your chosen worktops, not just how long the units take. Ask whether templating can be booked for the day the base units are finished, as every day saved there shortens the whole job.

What Slows a Kitchen Renovation Down?

Most delays come from deliveries, hidden problems, late changes and drying times. Very few come from the fitting itself. Knowing the common causes helps you avoid most of them.

Late, Missing or Damaged Deliveries

A kitchen is made of hundreds of parts. A damaged door or a missing cabinet can hold up one section while the rest carries on. Check deliveries the day they arrive and report problems straight away, so replacements can be ordered while work continues elsewhere.

Hidden Problems Behind the Old Kitchen

Older homes often hide surprises. Common examples include damp patches, rotten joists under the sink, out-of-date wiring and uneven walls. Each needs fixing before the new kitchen goes in. Keep a small contingency in your budget and your diary for this.

Changing the Plan Part-Way Through

Moving a socket before first fix is quick. Moving it after plastering means cutting into the wall, re-plastering and waiting for it to dry again. Fix the layout, appliance list and socket positions before work starts, and walk through them with your installer on day one.

Drying and Curing Times

Plaster, floor screed, tile adhesive and grout all need time. These waits cannot be rushed without risking cracks or loose tiles. New screed in particular can take weeks to dry, so a new concrete floor adds noticeably to the schedule.

Structural Work and Inspections

Removing a wall adds the steel beam, building control visits and making good around the opening. The kitchen cannot be fitted until that work is signed off. If your project includes a knock-through, expect at least an extra week or two.

Gaps Between Separate Trades

When the fitter, plumber, electrician, plasterer and tiler all work for different companies, each one has to fit you into their own diary. A day's gap between each trade soon adds a week. Having one team plan the whole sequence closes most of those gaps.

Kitchen Renovation Checklist: How to Keep Your Project on Time

Use this kitchen renovation checklist to stay on track from planning to handover. Most of the points take only a few minutes, but they prevent the delays that cost the most time.

Before Work Starts

  • Agree the layout, appliance list and socket positions in writing
  • Confirm delivery dates for units, worktops and appliances
  • Ask for a written timeline that shows each stage
  • Check whether building control approval is needed
  • Clear the kitchen and the route in from the front door
  • Set up a temporary kitchen and plan simple meals

During the Installation

  • Check every delivery against the order on arrival
  • Be available on day one and at first fix to confirm positions
  • Ask for templating to be booked as soon as base units are fixed
  • Raise any concerns early rather than at the end

At Handover

  • Open every door and drawer and run every appliance
  • Check sealant lines, grout and splashback edges
  • Collect electrical and gas certificates and any building control sign-off
  • Keep your warranty details and appliance manuals together

Planning Your Kitchen Renovation With Greentek

A kitchen renovation usually takes days for a refurbishment, one to two weeks for a like-for-like replacement and around 14 working days for a full renovation with stone worktops. The work on site follows the same order every time. Strip-out comes first, then first fix, plastering, units, worktops, second fix and handover. Good planning before day one is what keeps that order moving.

If your kitchen is part of a wider project, our full home renovation service plans the kitchen alongside the rest of the work, so trades are not waiting on each other.

Greentek Energy Ltd carries out kitchen renovations for homeowners across the UK. Our own fitters, plumbers, electricians and plasterers work in sequence, and every quote comes with a fixed price and a timeline agreed in writing before work begins. If you would like to know how long your kitchen would take, book a free survey and we will talk you through it.

Related articles

Frequently asked questions

How long does it take to remove an old kitchen?+
Removing a standard kitchen usually takes one day. The water, electrics and any gas supply are isolated first, then the units, worktops and appliances come out. It can take longer if wall tiles, old flooring or a chimney breast also need removing, or if anything suspicious is found that needs testing first.
Can I have a working sink while I wait for stone worktops?+
Sometimes. Some installers fit a temporary worktop and connect the sink so you have running water during the wait. It is worth asking about this at the quote stage, as it involves an extra visit to remove it later. If it is not possible, a utility room or bathroom sink can be used for washing up.
Do I need to be at home during the kitchen installation?+
Not all the time, but you should be available at key points. These are day one, when positions are confirmed, the first fix stage, the templating visit and handover. Someone also needs to let trades in and check deliveries. Many homeowners work from home on those days and leave a key for the rest.
How soon can I use my new kitchen after it is fitted?+
You can usually cook as soon as the hob is connected and tested. Leave new silicone sealant around the sink and worktops to cure before it gets wet, which normally takes about 24 hours. Grout needs a similar time. Check the product guidance, especially for stone worktop sealants and wooden worktop oils.
How far in advance should I plan a kitchen renovation?+
It is sensible to start planning two to three months before you want work to begin. That allows time for a survey, design changes, a fixed quote and ordering. Made-to-order units, stone worktops and any building control approval can all extend this, so start earlier if you have a deadline such as a family event.